When will work start?

The construction of all domestic vehicle pavement crossings shall be undertaken by the Council’s own approved contractor or a Contractor meeting the criteria listed below:

  1. All necessary permissions have been obtained
  2. The applicant has properly opened up the access and laid out the off-street parking provision (hardstanding) to the satisfaction of the Council
  3. Acceptable financial arrangements have been put in place and/or payment has been made.

Additionally, for external contractors, the contractor must provide to the Council:

  1. Evidence of the contractor’s public liability insurance (£5,000,000 minimum)
  2. Copies of the Supervisors and Operatives NRSWA Streetworks qualification cards (required under national legislation to undertake works on the highway).
  3. Confirmation that they are in possession of the Councils vehicle crossing installation standard details.
  4. Confirmation that they are in possession of full service/utility drawings for the location
  5. Evidence of previous experience of constructing vehicle crossings and are familiar with Traffic Management provision to Chapter 8 of the Traffic Signs Manual.

Once the above provisions are in place, construction will be programmed and the applicant informed of dates. The aim will be to commence construction within 6 weeks of these provisions being in place where the Council's contractor is used.