Willenhall cycleway – Abbey Road to Toll Bar End
Advance notice of road closures
Sunbury Road junction will be closed from Monday 9 November 2026 for 2 weeks to complete the raised table, drainage and new kerb lines. The diversion route will be via Stonehouse Lane.
Once this work is complete, work will take place at Stonehouse Lane which also requires a closure. We expect this work to start on Monday 23 November 2026 and it will take 2 weeks to complete.
Update 9 November 2026
- Temporary pedestrian crossing now in place for pedestrian access to Whitley football field
- Sunbury Road junction closed from Monday 9 November for two weeks
- Temporary lights to be in place from Abbey Road junction to Whitley Football field access between the hours of 9.30am to 3.30pm Tuesday 10 November and Wednesday 11 November to allow so that we can install a new kerb line towards Carnegie Close
- National Grid work at Carnegie junction now complete
Update 2 November 2026
- Abbey Road/London Road junction will have four way lights on Tuesday 10 and Wednesday 11 November. Off peak hours only.
- From Monday 2 November National Grid will be installing new electricity supply to Chace Hotel and will need some traffic management
- construction of the cycleway is now taking place from Abbey Road towards Chace Avenue
Update 26 October 2026
Advance notice of road closures
Sunbury Road junction will be closed from Monday 9 November for 2 weeks to complete the raised table, drainage and new kerb lines. The diversion route will be via Stonehouse Lane.
Once this work is complete, work will take place at Stonehouse Lane which also requires a closure. We expect this work to start on Monday 23 November and it will take 2 weeks to complete.
Other work includes:
- road narrowing traffic management will be in place from Carnegie Close to Abbey Road from Tuesday 27 October
- the Matrix electricity work outlined below could not take place and we will share revised dates here when we have them
Update 19 October 2026
Matrix contractors who are carrying out some electricity upgrade work will be carrying out work on the approach to Seymour Close. Although not part of our work, this will take place at the same time as work to minimise disruption.
They will then be working near to Folly Lane Boys Club from Friday 23 October to Tuesday 3 November. This will require two way lights. This is not part of our work.
Airport retail park splitter island relocation now complete.
Update 21 September 2026
Work is progressing well. At Seymour Close, a new kerb line and double height kerbs are being installed to stop vehicles cutting the corner and damaging the verge. Additional drainage will also be installed here following feedback from local people.
Update 1 September 2026
The majority of the surfacing work was completed at St James Lane. However, due to heavy rainfall there are some sections still outstanding that will be completed in the next few days.
The new traffic lights will be switched on around 10am on Wednesday 2 September and the temporary lights removed.
Tactile paving will be installed on Friday 4 September around the crossings which will then be opened up for use.
Update 24 August 2026
On Monday 24 August we will be installing all traffic lights ready for switch on once the surfacing works are complete.
Robert Close junction work starts on site Monday 24 August for around 3 weeks. Temporary lights will be in place here for 4 days. A temporary uncontrolled crossing will be set up and signed to divert pedestrians around the work area.
Update 17 August 2026
Construction of the crossing near St James Lane will begin on Monday 17 August, this is expected to take 4 days.
We have added a temporary pedestrian crossing at St James Lane
Work will start at Robert Close to remove the splitter island and associated work on Monday 24 August. Temporary lights will be in place for a week, followed by road narrowing.
Update 4 August 2026
Temporary lights at Abbey Road no longer needed and have been removed.
Additional pedestrian diversion signs have been added.
Update 17 July 2026
We will be moving onto the next phase of the work from Monday 13 July at the St. James Lane junction. This means there will be temporary lights from 9.30am on Monday morning, these will be monitored by our traffic team. Advance warning signs have been installed to advise of footpath closures and diversions around St James Lane whilst we complete the first part of this work.
The two-way lights at Sunbury Avenue have now been removed.
Background
Last year, we hosted two drop-in sessions to discuss plans to improve connectivity between Coventry city centre and Tollbar End. Thank you to everyone who attended one of the sessions, your feedback has helped to shape the next phase of this scheme.
The plans aim to make travel safer and easier for walking, wheeling, and cycling. The new design, shown below, builds on work around Abbey Road, London Road, and Humber Road.
Work will start in the area near Folly Lane Club and Kenelm Court on Monday 15 June 2026, with later sections delivered in phases. Work will include:
- 1km cycleway along London Road, mostly segregated, with two short (80m) shared sections for pedestrians and cyclists
- upgraded junction at St James Lane, with new toucan crossings and smart traffic signals that detect people and vehicles
- safer side-road crossings at Abbey Road, Carnegie Road, Seymoor Close, Sunbury Road, and Stonehouse Lane
- enhanced bus stops at Carnegie Close, St James Lane, and Stonehouse Lane for better flow, access, and passenger safety
- resurfacing, new signage, and road markings
- pavement improvements along the whole length for people walking and wheeling
- new parking area on the right of the green space opposite Folly Lane club. We will use a material that allows the grass to grow through it
Thanks to your feedback, we are also including the following:
- new pedestrian crossings at Folly Lane Boys club and Robert Close
- new signalised junction at Chace Avenue after comments received from consultation meetings
- there is currently no right turn in or out of Chace Avenue at London Road. This restriction will be lifted when the new signalised junction has been completed
Once the work in the area near to Folly Lane Club and Kenelm Court has been completed, work will take place at:
- St James Lane Junction
- Timeline: Mid-July – Early September 2026
- Traffic Management: Temporary signalised junction (remotely controlled to optimise traffic flow).
- Pilot Close
- Timeline: Early September – Early October 2026
- Traffic Management: Two-way temporary traffic lights
- Chase Avenue
- Timeline: Early September – Mid-October 2026
- Traffic Management: Chase Avenue will be closed for the duration of this phase, with two-way temporary traffic lights on London Road for one week only.
- Cycle Lane Installation
- Timeline: Early November 2026 – Completion in Spring 2027
We will keep this page updated as work progresses.

Your feedback
In November last year, we asked what you thought of the plans. You can see the feedback we received and our responses to that feedback.
Road safety audits
All cycle schemes are subject to three detailed safety audits. There are three stages: one at the start of the design process, one that is carried out during construction, and a final audit on completion of the work. Safety audits are an essential part of cycle schemes as they help to ensure that our plans are reviewed independently.
An independent team carries out the safety reviews. These are now available to view.
You can see London Road South feedback responses.