Headline progress - The One Coventry Plan 2022 to 2030

The One Coventry Plan 2022 to 2030 is measured against 74 metrics. Seven are unable to be reported for this year (or at the end of 2024 to 2025) as information is not available. Also, 1 has not been fully developed – these 8 are recorded within the ‘progress not available' indicators.

Of the 66 metrics currently available, for 5 of them we cannot say whether they have improved or not because there isn’t a clear desirable direction of change or because we only have data for this year.

One coventry plan 2024 to 2025 p9

In summary 67% (41 out of 61) of the ‘directional’ indicators available, improved or stayed the same.

Increasing the economic prosperity of the city and region

14 headline indicators for 'Increasing the economic prosperity of the city and region', of which
Tick 9
Cross 3
Barrier 2

Improving outcomes and tackling inequalities within our communities 

21 headline indicators for 'Improving outcomes and tackling inequalities within our communities', of which

Tick 10
= 2
Cross 7
? 1
Barrier 1

 Tackling the causes and consequences of climate change

22 headline indicators for 'Tackling the causes and consequences of climate change', of which

Tick 9
= 1
Cross 6
? 2
Barrier 4

Continued financial sustainability of the Council

17 headline indicators for 'Continued financial sustainability of the Council', of which
Tick 6
= 4
Cross 4
? 2
Barrier 1

There is 1 indicator which is not fully developed, within the ‘Tackling the causes and consequences of climate change’ priority:

  • biodiversity net gain (measure of tree planting and biodiversity), has recently been incorporated into national planning policy and, in future, registration of offsetting sites with Department for Environment, Farming and Rural Affairs will be available to measure this. Data on biodiversity units and habitat enhancement will be provided from next year